From Realtà Mapei n° 33 - 5/17/2021

MAPEI and Mose save Venice from Flooding

17 years after work started, the system of dams designed to stop high tides made its debut. Several MAPEI were especially designed to build the system.

These articles are reprinted from Realtà MAPEI International magazine, Issue #83.

The MOSE floodgates in the Venetian lagoon were raised on October 3, 2020. By 10:15 am, all 78 gates were in position, and expectations were high as the system began its first real test under critical conditions. The difference in levels between the sea and the lagoon soon rose to 40 cm. As the world watched, the level of the lagoon did not rise any further and Venice was not flooded.

That was the first official test for a structure that had taken almost two decades to build and that was designed to protect Venice from high tides, events that have become all too common.

 

A long-awaited project

MOSE (an acronym for MOdulo Sperimentale Elettromeccanico, or Experimental Electromechanical Module) is a hydraulic structure designed to hold back water if it rises above a certain level. The specific MOSE system in the Venetian lagoon is designed to protect Venice and the lagoon from high tides of up to 3 meters and from a 60-cm rise in sea levels over the next 100 years.

The structure is like an automated dam, with 20-meter-wide barriers in various thicknesses that use their own weight and the force of gravity to help them operate. The idea for this kind of system was first suggested 40 years ago. Following numerous delays and public inquiries, construction work commenced 20 years ago and is scheduled to be fully complete by the end of 2021.

The system consists of 78 mobile steel floodgates measuring up to 29 meters in height. Each gate operates independently. The system is able to isolate the lagoon from the sea during high tides. Other works have also been carried out in the area, such as reinforcing stretches of coastline outside the entrances to the port to alleviate the effect of normal tides, and raising quaysides and paving in the lowest areas of the inhabited areas around the lagoon.

The floodgates are housed in concrete caissons positioned on the seabed at the entrances to the three ports of the lagoon – Lido, Malamocco and Chioggia – and are designed to be raised when the tide exceeds a level of 110 cm.

 

Outlets to the open sea

The MOSE system is made up of four barriers positioned at the three outlets to the open sea. The widest outlet – which is the one closest to Venice – is positioned at the Lido entrance and is made up of two channels, each with a different depth. There are two barriers to protect this outlet: The north barrier, which is made up of 21 floodgate modules, and the south barrier with 20 modules. The two barriers are connected by an artificial island where the equipment used to operate and maneuver the system is located.

The entrance to the port of Malamocco is the deepest in the lagoon. This is the one used by ships heading to the industrial and commercial port, so a navigable basin has been constructed for the ships. The barrier at this entrance is made up of 19 floodgates.

The entrance to the port of Chioggia is used mainly by fishing boats and pleasure craft, and a sheltered port with a double navigable basin has been constructed so that boats can enter and exit the port, even when the barrier is closed. This opening is protected by 18 floodgates.

 

How the MOSE system works

When the floodgates are in stand-by mode, they are completely invisible, full of water and sitting in caissons on the seabed.

When there is a high tide that could potentially flood the surrounding area, compressed air is pumped into the gates to displace the water. As the water is expelled from the floodgates, they swivel on their hinges, rise out of the caissons and block the entrances to the lagoon. On average, the time required for the floodgates to seal off the port entrances – including the time required to maneuver the floodgates into position – is four to five hours.

The gates only remain in this position during high tide. When the tide ebbs and when the lagoon and the sea reach the same level, the floodgates fill with water and then retract into their housing.

Each floodgate is made up of a hollow metal structure that is attached to the caisson housing with two hinges. Each is 20 meters wide, while their height depends on the depth of the port entrance channel where they are positioned, and their thickness also varies.

The caissons housing the floodgates and the mechanisms used to maneuver them form the base of the barrier and are connected to each other by an inspection tunnel.

The structure that connects the barriers to dry land is made up of large support housings that contain all the equipment required to make the gates operate correctly.

MAPEI solutions for the MOSE project

MAPEI took part in the MOSE project as a technical partner, and a dedicated team of MAPEI specialists regularly interfaced with design engineers, works directors and contractors. The company’s Technical Services, working in tandem with the Research & Development laboratories, proposed several special, innovative, high-performance products.

 

Grouting the joints

Mapefill MF 610* was specifically developed for this project. It was used for grouting the joints and creating the watertight seal required in order to connect them with their matching fittings on the caissons housing the floodgates.

The caisson housings were positioned in sequence in a trench and were connected together with a special jointing system made up of two separate elements to form a watertight seal. The first element of the system is the so-called “Gina ring-joint,” which keeps the external part watertight and forms a temporary watertight seal between one caisson and the next one while they are being installed. The second element is the “Omega seal,” which is installed inside the Gina joint during construction of the caissons and guarantees that the entire caisson remains watertight.

A grout with high compressive strength to withstand the rigors of the joints was required for this job. The grout would be required to maintain a high level of workability at high temperatures (around 3 hours at +35°C). The Gina collar used to house the joint was made from super-duplex stainless steel, an extremely expensive material that left no margin for error during installation. After many tests and working closely with MAPEI’s R&D and Technical Services teams, the Gina joint was connected to the concrete caisson by pumping Mapefill MF 610 into formwork.

Mapefill MF 610 is a fiber-reinforced powdered grout made from high-strength cement, select aggregates, special admixtures and polyacrylonitrile synthetic fibers. When mixed with water, it forms a fluid grout that does not segregate and is able to flow even into oddly shaped spaces. The product has low capillary absorption (complying with EN 13057), is highly impermeable to water, adheres very strongly to iron and concrete, and is highly resistant to mechanical stress, including dynamic stress.

Thanks to its performance characteristics, Mapefill MF 610 fulfilled all the client’s requirements during both the application phase and the qualification tests.

 

Anchoring the hinges and waterproofing the caissons

The metal floodgates are anchored to the reinforced concrete caissons with a hinge mechanism, which allows them to be raised and lowered depending on the dangerously high tides. As Enrico Pellegrini, former site manager for Grandi Lavori Fincosit SpA, explains in the accompanying interview, anchoring the hinges to the caissons required a great deal of design work and testing to identify the most appropriate products and technology in order to fasten a metal component, in this case the hinge, to concrete.

MAPEI specifically developed Mapefill MF* for this application. Mapefill MF is an expansive, fluid mortar that was used for anchoring the hinges onto the concrete caissons in specific positions with great precision. The mortar was applied by injecting it into one side of the hinge, and then it flowed to perfectly saturate all the gaps and free spaces to form a single, solid body with the caisson onto which it was anchored.

The waterproofing system for the caissons, which are then placed on the seabed, also had to be carefully designed and thoroughly tested in order to identify products that would guarantee excellent, long-lasting results. After tests were performed on site and in the lab, the external surface of the caissons was treated with MAPEI’s Mapelastic Foundation*. This is a two-component, flexible, cementitious mortar for waterproofing concrete surfaces subjected to both negative and positive hydraulic pressure.

The product chosen for the inside of the caissons, on the other hand, was Mapelastic two-component, flexible cementitious mortar. It was applied after treating the substrates with a specially designed version of Primer 3296*.

This part of the work, as with the challenge of anchoring the hinges, was closely followed by the MAPEI Research & Development Laboratory in Milan, which carried out testing on the application of the products for the entire duration of construction.

 

Source of information in the article: Italian Ministry of Infrastructures and Transport - Interregional Department of Public Works for Veneto - Trentino Alto Adige - Friuli Venezia Giulia, former Magistracy for the Waters of the Province of Venice

* Although Mapefill MF 610, Mapefill MF, Primer 3296 and Mapelastic Foundation are not currently available in the North American market, this article highlights MAPEI’s systemsolution approach to jobsites and our ability to develop products to meet specific needs. How may we help you? For more information, please contact our Customer Service Department at 1-800-42-MAPEI.

 

Enrico Pellegrini

HOW WE SOLVED THE PROBLEM OF THE HINGES
The hinges for the barriers are the technological heart of the mobile barriers

An interview with Enrico Pellegrini, former site manager for Grandi Lavori Fincosit SpA

 

 

Q: Mr. Pellegrini, what role did you have in the MOSE project?

A: From 2005 to 2015 I was the manager of the site where the precast concrete caissons were manufactured for the inlets to the ports of Lido San Nicolò and Malamocco. The site was located on a 13-hectare artificial embankment created specifically for the project on the island of Pellestrina.

Q: Which part of the work on the MOSE project proved to be the most challenging with regards to its design and the materials to be applied?

A: The structure of the MOSE barriers is made up of two main elements: The reinforced concrete caissons, which anchor the barrier to the seabed, and the metal floodgates, which are those big, yellow boxes that we can see rising up out of the sea to stop high tides. The two elements are joined together by a highly sophisticated device: The hinge. The caissons are fixed permanently to the seabed, whereas the metal floodgates can be periodically removed to carry out scheduled maintenance work. This means that the hinge element must allow the floodgates to be disconnected from the caissons, which is why it is made out of two parts: The female part, which is permanently fastened to the caisson, and the male part, which is an integral part of the floodgate. To anchor the steel female part to such an enormous reinforced concrete structure (the largest caissons are as big as a three-story apartment block) with pinpoint precision was a really challenging design and construction matter, which we managed to overcome by applying materials of the very highest quality and by planning the application procedures down to the minutest details.

Q: What problems did you have to overcome to anchor the hinges in place?

A: It was extremely important that the female hinges can be replaced and maintained at regular intervals; this won’t be possible for the concrete caissons. The difference of the two materials (reinforced concrete and steel), in terms of thermal and elastic behavior, the difference in the design codes and construction methods applied, as well as the need to create a seal that would remain perfectly watertight at a great depth, required a very careful, in-depth study of the behavior of the two elements when joined in one single element. This is why Mapefill MF was chosen: A product that would be able to guarantee the maximum level of adhesion between the two elements, with high mechanical properties, while maintaining sufficient elasticity and the ability to be distributed into any tiny gaps in the spaces left to connect the two elements together.

Q: Any structure immersed in water must be fully waterproof. What were the most significant characteristics of this part of the work?

A: As I mentioned previously, while the floodgates will have to be extracted so their protective waterproofing system can be replaced and maintained at regular intervals, this won’t be possible for the concrete caissons. This made it extremely important to design one or several systems that would completely waterproof the structure. This is why, for the construction joints, three waterstop systems were provided, with the external one coated with a cementitious waterproofing membrane. In spite of all these precautions, after carrying out a thorough analysis of the costs and benefits, the contractor decided on site to integrate these safety systems even further by treating the entire surface of the caissons, from top to bottom, with a specially designed formula of Mapelastic Foundation mortar, which was further integrated by applying a coat of a primer specifically designed by the MAPEI R&D laboratories.

Q: Because of the new materials and technologies adopted, do you think the MOSE site can be considered a pilot project for other sites of this type?

A: Obviously, I can only speak for the work carried out on the site, with which I was involved, but I would say that, more than anything else, it was the way the project was managed from a technical point of view that could be used as an example of how to set up a major works site. One such example is the care taken in choosing the right materials, which was dictated not only by the principles of affordability, but also by means of a long series of tests and cost/benefit evaluations.

Q: You worked very closely with MAPEI Technical Services and the company’s R&D laboratories in Milan. How did this team approach work exactly?

A: I was in no doubt about Mapelastic’s waterproofing capacity and elasticity, but I was still concerned about two factors: How strongly it would bond to the substrate and its durability. That’s why I personally wrote out a procedure that included an extensive range of tests to be performed on site to demonstrate which would be the best technology to prepare the base, but also which was the best primer to apply in order to guarantee the highest level of adhesion for the membrane. The MAPEI product performed better than those of the competitors, thanks also to the direct and prompt interest shown by the company’s R&D lab, which made some slight modifications that greatly improved its final performance properties. Besides, it was really comforting to be able to rely on an experiment carried out by the laboratory at the Polytechnic of Milan, which demonstrated that Mapelastic maintains its performance properties even after a series of extended immersion cycles in seawater.

Also, worth highlighting is how the MAPEI lab followed our progress throughout the entire construction, which lasted around one year, by coming to monitor and test the application of the product on a regular basis. We found this to be very reassuring, and it provided us with a further guarantee of the final quality of the work we carried out on site.

Keep in touch

Subscribe to our newsletter to get Mapei news