Dvorišče | The works included dredging the harbour in stages (approx. 9 500 m³) and carrying out civil engineering works, surface repairs and reconstruction of the mooring facilities. |
---|---|
Položaj | Versoix, Switzerland |
Podkategorija | HARBOUR |
Vrsta uporabe | During the work, the harbour remained in operation. There were 25 workers and two diving teams working during peak hours. The new bridge stands on five piles and 500 m2 of slabs were laid. |
Vrsta uporabe | Rešitve za marine program |
Izvajalsko podjetje | Ingénieurs civils : B+S Ingénieurs SA – Genève GEOS Ingénieurs Conseils SA - Lausanne |
Inštalacijska podjetja | Groupe Orllati SA – 1042 Bioley-Orjulaz |
Vodja projekta | République et canton de Genève |
Koordinacija MAPEI | Alexandre Perona |
Tukaj se lahko naročite na Mapei novičnik in prejemate naše novice