Gordes wastewater treatment plant (STEP)

Location icon GORDES, France
Ref. št.: 6123
Kategorija: ZANIMIVOSTI

Gradbeništvo

Dvorišče Gordes wastewater treatment plant (STEP)
Položaj GORDES, France
Podkategorija
Vgrajeno 2023
Otvoritev 2023
Vrsta uporabe Supply of admixtures for making concrete
An aggressive chemical environment, pouring in hot weather, dense reinforcement and easy implementation are the constraints to which Sylvestre Béton and MAPEI have responded. The admixture chosen, DynamonEasy833 and MAPETARD, was one of the keys to the formulation. More than 2,500 m3 of C35/45 XA2 D16 S4 concrete were used by 4MMEREU BTP, the company building the WWTP.
Datum začetka in konca 2023
Vrsta uporabe Oskrba dodatkov
Izvajalsko podjetje Sylvestre Béton
Inštalacijska podjetja 4MMEREU TP
Koordinacija MAPEI Mikaëlle Astier

Ostanite v stiku z nami

Tukaj se lahko naročite na Mapei novičnik in prejemate naše novice