Područje primene | highway bridge |
---|---|
Lokacija | Agigea, Rumunija |
Kategorija objekta | MOST |
Godina izgradnje | 2002 |
Otvoren | 2015 |
Radovi izvedeni Mapei materijalima | concrete repair and protective coat application |
Vreme izvođenja radova | 2014 |
Vrsta radova | Fasaderski radovi |
Investitor | GRUP SERVICII PETROLIERE |
Glavni izvođač | APOLODOR IMPEX SRL |
Podizvođač | AGNEL INDUSTRY SRL |
MAPEI distributer | AGNEL INDUSTRY SRL |
Opis | MAPEI contribution was to protect concrete structures against carbonation using the most suitable products. The piles were poured using SCC; one of the piles had some honey combs and cracks due to some problems in the pouring process. The cracks were consolidated by injecting Epojet and the concrete was reprofiled by pouring Mapegrout Colabile. |