Application steps

1
Concrete substrate – Slope 1/4" per foot (6 mm per 0.30 m)
2
Planiseal CR1 waterproofing membrane applied at 60 mils – 1st coat
3
Overlap MAPEI LMR Fabric approximately 1" (2.5 cm) – embed into 1st coat of Planiseal CR1
4
Planiseal CR1 waterproofing membrane applied at 60 mils – 2nd coat
5
Mapedrain 35 drainage composite
6
Concrete topping slab