MAPEI is one of the Italian manufacturers that contributed with their own-brand products to the construction of the New Bridge in Genoa, designed by the architect Renzo Piano and built by Webuild and Fincantieri Infrastructure.
For this particular project, MAPEI supplied admixtures for the ready-mixed concrete used to make the piers and the floor slab. Then MAPEI supplied a team of technicians and specialists, working round the clock, from when work first started up until the placing of the final cubic meters of concrete.
MAPEI also supplied solutions for the repair, strengthening and waterproofing the access ramp that connects the San Giorgio Bridge to the A7 Motorway on the eastern side.
“We are pleased to have played a part in the construction of the New San Giorgio Bridge in Genoa,” commented Veronica Squinzi, MAPEI CEO. “And supplying solutions which are certified and durable has always been our mission.”
Technologies and systems were proposed by MAPEI along with the Technical Services team supplied by the company. And the designers, the manufacturer of the concrete and the main contractor’s engineers contributed through continual discussions and feedback. All of these played an important part in completing the most important infrastructure in Italy for decades, a true symbol of reconstruction, commitment and the desire to recover.
“Less than two years following the collapse of the Morandi Bridge, and especially today when the memory of this tragedy is more alive than ever, the inauguration of the New Bridge is a clear demonstration of how the dedication, commitment and passion people have for their work can help create something exceptional and sustainable,” added Marco Squinzi, MAPEI CEO.
The bridge is made up of a steel and concrete deck and a 1,067-meter truss divided into 19 spans (14 spans of 50 meters, 3 spans of 100 meters, 1 of 40.9 meters and 1 of 26.27 meters) with the whole structure supported by 18 reinforced concrete piers with an elliptical section.
The gentle forms of the bridge, from its elliptical piers to the deck similar to the hull of a ship, and the light tones of its elements, help the structure blend in with the surrounding landscape.
The 18 reinforced-concrete, elliptical piers were made by placing the concrete in a continuous cycle using climbing formwork, special formwork that is attached to the actual structure using the concrete placed earlier as a support base. When the new concrete is poured, the previous concrete must already have certain mechanical properties in order to bear the weight not only of the formwork, but also of the new concrete.
The piers were constructed between June 2019 and January 2020. The various operations were carried out in different weather conditions and at different temperatures, which had an influence on the type of admixtures employed, leading MAPEI to proposing a combination of various products.
The combination of cutting-edge admixtures, which are used to modify hydration reactions and the hardening rate of cementitious materials, meant that the results expected were achieved in complete safety and guaranteed that the mechanical properties between the various concrete pours remained constant. The admixtures utilized were:
The final requirement, and one that was particularly important to the client, was that the exposed surfaces should have an excellent finish once the formwork had been removed, with no defects and a uniform color, and that it should enhance the materic effect of the perfection of the element. The result was achieved brilliantly, thanks not only to the correct mix-design, but also to the use of a special form-release agent with the ability to guarantee such a high-quality and attractive finish. After a series of mockups on site, it was decided to use MAPEFORM W60, a form-release solution in water dispersion for concrete with a high-quality finish.
Once assembly of the metal framework for the deck had been completed, MAPEI was involved in the second phase with products for the concrete pour for the floor slab, which was made using compensated-shrinkage concrete to prevent the formation of shrinkage cracks.
This operation was carried out in June 2020. In this case too, various design factors had to be taken into consideration, such as the particularly high mechanical properties required and the rate of compensated-shrinkage that had to be maintained to within specified limits. Plus, as an aspect particularly important for the actual placing and finishing operations of the concrete, the project had to have extended workability in hot weather and be able to achieve high mechanical properties after a short curing cycle to facilitate leveling and surface-finishing operations.
As in the case of the piers mentioned previously, achieving the required results was made possible by using a combination of specific products:
To minimize the evaporation of water, which could lead to the onset of crazing, the following was used for the kerbstones along the sides of the slab:
Repair and strengthening work was carried out on the foundations, the piers and the deck of the viaduct. The products used for the piers and vertical features were:
Products used for the intrados and extrados of the bridge deck were:
The slab for the access ramp was waterproofed with: