Yard | Lambert Airport, Runway Expansion |
---|---|
Location | St. Louis, USA |
Subcategory | AIRPORT |
Application | Lambert Airport, Runway Expansion |
Application Type | New building, Admixtures for concrete |
Contractor company | Millstone Bangert |
Other |
266,000 cubic yards of concrete poured to withstand a harsh freeze/thaw environment. Millstone- Bangert poured 5,000+ cubic yards of consistent 6% air entrained, low slump, slipformed concrete 18″ thick for 40 days. Consistency of concrete was key to maintianing the aggresive pour schedule this project required. Photos courtesy of Lambert St. Louis International Airport |