"Yard" | Business Park |
---|---|
"Location" | Singapore |
"Subcategory" | MALL |
"시공 시기" | 2014 |
"오픈 시기" | 2016 |
"Application" | installation of ceramics and stone materials inside and outside |
"Start and finish date" | 2015/2016 |
"Application Type" | Installation of floor and wall coverings |
"Owner" | Shimizu Corporation |
"Contractor company" | Shimizu Corporation |
"Installer companies" | CSC Holdings Limited, Yangzijian International (S) Pte Ltd |
"Architects" | DCA Architect |
"MAPEI Distributor" | Mapei Far East Pte Ltd |
"마페이 조정" | Ryan Liaw (Mapei Far East, Singapore) |
"설명" | Soon after the completion of MBC phase 1, major issues on the tile bonding surfaced. Installation materials were supplied by Laticrete. Tiles from the toilets debonded causing potential danger. At the request of the owner, Mapei did a thorough site inspect |