Chantier | highway bridge |
---|---|
Localisation | Agigea, Roumanie |
Sous-catégorie | PONT |
Construit en | 2002 |
Ouvert en | 2015 |
Demande | concrete repair and protective coat application |
Date de début et de fin | 2014 |
Type de demande | Finitions murales |
Titulaire | GRUP SERVICII PETROLIERE |
Entreprise de sous-traitance | APOLODOR IMPEX SRL |
Installateurs | AGNEL INDUSTRY SRL |
Distributeur MAPEI | AGNEL INDUSTRY SRL |
Other | MAPEI contribution was to protect concrete structures against carbonation using the most suitable products. The piles were poured using SCC; one of the piles had some honey combs and cracks due to some problems in the pouring process. The cracks were consolidated by injecting Epojet and the concrete was reprofiled by pouring Mapegrout Colabile. |