场地 | The works included dredging the harbour in stages (approx. 9 500 m³) and carrying out civil engineering works, surface repairs and reconstruction of the mooring facilities. |
---|---|
位置 | Versoix, 瑞士 |
子目录 | 港口 |
施工 | During the work, the harbour remained in operation. There were 25 workers and two diving teams working during peak hours. The new bridge stands on five piles and 500 m2 of slabs were laid. |
施工类型 | 航运业应用 |
承包商公司 | Ingénieurs civils : B+S Ingénieurs SA – Genève GEOS Ingénieurs Conseils SA - Lausanne |
安装公司 | Groupe Orllati SA – 1042 Bioley-Orjulaz |
项目经理 | République et canton de Genève |
马贝协调员 | Alexandre Perona |