Gordes wastewater treatment plant (STEP)

Location icon GORDES, France
N° réf. : 6123
Catégorie : ART/DIVERS

Réalisation

Chantier Gordes wastewater treatment plant (STEP)
Lieu GORDES, France
Sous-catégorie
Construit en 2023
Ouvert en 2023
Application Supply of admixtures for making concrete
An aggressive chemical environment, pouring in hot weather, dense reinforcement and easy implementation are the constraints to which Sylvestre Béton and MAPEI have responded. The admixture chosen, DynamonEasy833 and MAPETARD, was one of the keys to the formulation. More than 2,500 m3 of C35/45 XA2 D16 S4 concrete were used by 4MMEREU BTP, the company building the WWTP.
Date de début et de fin 2023
Type d’application Adjuvants pour béton
Entrepreneur Sylvestre Béton
Installateurs 4MMEREU TP
Coordonnateur MAPEI Mikaëlle Astier

Keep in touch