Chantier | Klang Valley Mass Rapid Transit (KVMRT) |
---|---|
Localisation | MALAISIE |
Sous-catégorie | MÉTRO |
Construit en | 2013 |
Ouvert en | 2014 |
Demande | Klang Valley Mass Rapid Transit (KVMRT) - Bukit Bintang Central Underground Station |
Date de début et de fin | 2013/2014 |
Type de demande | Impermeabilisation |
Titulaire | Mass Rapid Transit Corporation Sdn Bhd |
Entreprise de sous-traitance | MMC Gamuda KVMRT (T) Sdn Bhd |
Installateurs | CRT Specialist (M) Sdn Bhd |
Architectes | Mott MacDonald (M) Sdn Bhd (Engineers) |
Distributeur MAPEI | Mapei Malaysia Sdn Bhd |
Other | The Bukit Bintang Central station is constructed using the “cut-and-cover” method with a total excavation depth of 33m. It has a footprint of 150m x 19.0m with depths of 16.9m from existing ground level to the top of rail level for the upper platform and 30.4m to the top of rail level for the lower platform. The station consists of four levels namely concourse, upper platform, plant-room platform and lower platform. The main contractor wanted a durable, high-performance waterproofing system, "MAPEI Purtop" for the roof slab to provide long-term, low-maintenance protection against water ingress. (The walls were protected using a drainage system.) |
Copyright © 2024 MAPEI BENELUX S.A. Tous droits réservés.
Mapei Benelux S.A. Rue de l'Avenir, 40 4460 Grâce-Hollogne - Belgique
Tel +32-04-2397070 - mapei@mapei.be - TVA BE0455 328 589