Art der Baustelle | The 35.5-metre-high grain silo with 19 interior grain chambers has space for 2 800 tonnes of grain. The grain silo was built in 24-hour operation. Construction took a total of 212 hours, or just under nine days. |
---|---|
Standort | Hallau, Schweiz |
Unterkategorie | SILOS |
Anwendung | The new construction of the additional grain silo in Hallau was built in 24-hour operation. The building was erected using slipforming, which was raised in three-minute cycles. |
Anfangs- und Abschlussdatum | 2022 |
Art der Anwendung | BETONINSTANDSETZUNG |
Installationsunternehmen | KIBAG Beton AG |
Projektmanager | Neumühle Hallau GmbH |
Koordinierung von MAPEI | Reto Märki |